TOWN CENTRE REGENERATION STOCKTON
PROJECT STATS
Balfour Beatty Construction Value: £3.1m Start date: June 2012 Contract length: 28 months
TESTIMONIAL

 

"I have worked with Addison Plant Ltd on and off for 20 years and recently completed a public realm scheme in regenerating Stockton High St. This was a two year project upgrading the bus routes and hard landscaping.
I was very impressed with APL’s attitude regarding safety and their consideration to the public as this is a busy High St with events been held throughout the year. The safe digging practices employed resulted in zero service strikes which is highly commendable due to the complex network of services and underground tanks/cellars encountered.
The works consisted of drainage, ducting, earthworks and street furniture with the value of circa £3m and a large number of site operatives at any one time."
ADAM FOWELL BEng (Hons)
Balfour Beatty Construction Services UK
PROJECT SUMMARY The regeneration of Stockton Town Centre will provide an area of public space that will attract investment and business, whilst also providing an improved environment for residents and visitors. 
It will also be flexible enough to facilitate a wide variety of events. The project will include the realignment of the existing highway including the introduction of bus turning facilities, demolition of an existing building and the introduction of areas of car parking as well as a new public realm scheme covering the area including new paving, street furniture and landscaping incorporating a water feature. Our work included: Extensive trial holing or slit trenches using our Air Vac Machine to locate all existing services. Excavating & disposal of existing paving & kerbing. York stone was saved for re use. Installation of tree pits 3m x 2m x 1.5m deep and heavily reinforced lighting column bases 2.5m x 2.5m x 1.8m deep. Surface water drainage including connections to Northumbrian Water sewers. Traffic signals and street lighting ducts. Forming a 100mm thick concrete slab over the whole area on which new pavement is laid. Night shifts and Sunday work was implemented to move bus stops including bus kerbs & road crossings as well as work in shop doorways maintaining access.
CONTACT US
BEFORE
AFTER
Telephone 01642 602666